Production costing and reports
Understand what a finished item costs and use reports to monitor production.
Plan availability
Available with the Production add-on, which any plan can add. Contact us to add it.
Overview
When you finish a work order, the finished item receives a valuation rate equal to the cost of materials used, plus operation costs and additional costs. This is your cost of goods for those items.
How cost is built
| Part | Where it comes from |
|---|---|
| Raw materials | Valuation of the materials consumed |
| Operating cost | Time on a workstation times its hourly rate |
| Additional costs | Costs added in the Manufacture stock entry, such as electricity or packaging |
| Scrap | Value recovered from scrap items reduces the cost |
To add costs, open the Manufacture stock entry and use the Additional Costs table before submitting.
Reports
Search for these reports.
| Report | Shows |
|---|---|
| Work Order Summary | Status and quantities of every work order |
| Production Analytics | Output by period |
| BOM Stock Report | Whether you hold enough stock to make each BOM |
| Work Order Consumed Materials | Materials used against what the BOM expected |
| Cost of Poor Quality | Losses from rework and scrap, if tracked |
| Stock Ledger | Every movement of materials and finished goods |
Practical example
A work order was expected to use 50 kg of flour but used 56 kg. The consumed materials report flags the 6 kg variance. The manager checks for waste and adjusts the BOM if the real recipe needs it.
Important notes
- Costing is only as accurate as your purchase rates and BOM quantities.
- Review variances monthly and correct the BOM when reality has changed.
- Ask your accountant how to treat labour and overheads for tax and reporting.
Common mistakes
- Never updating BOM costs after prices change.
- Recording additional costs outside the system, so the unit cost is too low.