Documentation/Manufacturing/Job cards and production planning

Job cards and production planning

Track operations and time on the shop floor, and plan production from sales orders.

AdvancedAbout 25 minutesVersion 1.0Updated 17 November 2026

Plan availability

Available with the Production add-on, which any plan can add. Contact us to add it.

Overview

Job Cards record the work done at each operation. A Production Plan looks at your sales orders and stock and works out what to make and what to buy.

Prerequisites

BOMs with operations and workstations. Create each Workstation (search for it), with its working hours and hourly cost.

Steps

Job cards

  1. Create a work order for a BOM with operations. A Job Card is created for each operation.
  2. The operator opens the Job Card, clicks Start Job, works, and clicks Complete. The Time Logs record how long.
  3. Enter the Completed Qty. Submit.

Production plan

  1. Search for Production Plan and click Add.
  2. Under Get Items From, choose Sales Order, and click Get Sales Orders, or add items by hand.
  3. Click Get Finished Goods for Manufacture. The plan lists the items to make and the raw materials needed.
  4. Click Get Raw Materials for Purchase to see what to buy, or Get Raw Materials for Transfer for materials to move from another warehouse. The plan adjusts for stock already on hand.
  5. After submitting, click Create > Work Order / Subcontract PO, or create a Material Request from the plan.

Practical example

On Monday the production manager plans the week: five customer orders need 40 chairs. The plan shows enough timber for 30, so it raises work orders for 40 and a material request for the missing timber.

Important notes

  • Job cards give you real times and costs per operation. Use them if labour is a large cost.
  • A plan is only as good as the stock figures. Do a count first. See Opening stock and stock counts.

Common mistakes

  • Planning without checking existing work orders, which duplicates production.
  • Skipping the operator's time logs.

Next steps

Read Production costing and reports.